Public utility works: Leith Area

(adapted from an email from Graham Hall (CEC Senior Transport Team Leader) to Leith ward and Leith Walk ward councillors; with thanks to the councillor that forwarded it to community councils. This information reached LHNCC’s webmaster today [19 July].)

As you will be no doubt aware, The City of Edinburgh Council is carrying out significant pre-tram surfacing works in wards 12 and 13 at the current time via our Transport Design and Delivery section who have McLay’s Ltd carrying out numerous projects in preparation for the Tram extension works which are due to commence later this year.

In addition to these works City Fibre have started their programme to install fibre to the home in the area as well as the other utility providers continuing their business as usual.

It has been agreed with the CEC project manager (Steven Blacklaw) that the locality will coordinate these works around his significant programme to avoid conflict with different sets of work. As McLays Ltd are based in Airdrie and traditionally close down for the Glasgow Fayre fortnight commencing on the 12th of July I have delayed various utility works commencing until McLay’s have closed their sites down and to prevent additional pressure on the road network. The works below have been approved for the period 14th July 2019 to 30 July 2019 to avoid any conflict with the CEC programme.

Whilst there will no doubt be some form of delay caused by the various works, please be assured that every effort has been made to minimise disruption utilising the quieter school holiday period whilst still ensuring these works are completed before CEC’s contractor returns to recommence his programme. Please also note that where required, any works which may present significant disruption have been discussed and approved at the City Wide Traffic Management Group to ensure the most effective traffic management is employed.

Should you have any further questions please do not hesitate to call on the number below.

Utility Location Nature of works Works Start Finish Traffic Management
City Fibre Salamander Street Installing new fibre optic cable TBC TBC Two way temporary traffic signals
City Fibre East Hermitage Place Installing new fibre optic cable 14/07/2019 17/07/2019 Three way temporary traffic signals
Scottish Power Albert Street Main Cable repair 15/07/2019 19/07/2019 Parking Restriction only
Scottish Power Constitution Street Install new service 19/07/2019 23/07/2019 Parking Restriction only
Scottish Power Pilrig Street at Dryden Street Excavate footway to replace joint TBC TBC Parking Restriction only
Scottish Gas Networks Newhaven Road at Graham Street Install new connection to gas main 14/07/2019 30/07/2019 Three way temporary traffic signals
Scottish Gas Networks North Junction Street at Ferry Road Replace existing gas main 14/07/2019 30/07/2019 Three way temporary traffic signals
Virgin Media Lindsay Road at Sandpiper Drive Install new service 15/07/2019 19/07/2019 Lane restrictions and local diversion

Graham Hall – FIHE – Senior Transport Team Leader – Place – City of Edinburgh Council – North East Locality, 101 Niddrie Mains Rd, Edinburgh, EH16 4DS – Tel: 0131 469 3926 – Northeast.transport@edinburgh.gov.uk

Please note: all correspondence should be sent to Northeast.transport@edinburgh.gov.uk

Tram plans

These were downloaded from http://www.edinburgh.gov.uk/tramstonewhaven and are presumably © their creators and/or Edinburgh Council.

Landscape proposals

Traffic management proposals

  1. Phase_1___Albert_Street___Elm_Row
  2. Phase_1___Constitution_Street___Queen_Charlottle_Street
  3. Phase_1___Constitution_Street___Steads_Place
  4. Phase_1___Newhaven___North_Leith_Sands
  5. Phase_1___North_Leith_Sands_to_Ocean_Terminal_Southside
  6. Phase_1___Ocean_Terminal_Southside
  7. Phase_1___Ocean_Terminal
  8. Phase_1___Steads_Place___Albert_Street
  9. Phase_2___Foot_of_the_Walk_to_Manderston_Street
  10. Phase_2___Ocean_Drive___Tower_Place
  11. Phase_2___Ocean_Terminal___Ocean_Drive
  12. Phase_2___Picardy_Place___Union_Street
  13. Phase_2A___Queen_Charlottle_Street___Coatfield_Lane
  14. Phase_2B___Stevedore_Place___Constitution_Street
  15. Phase_2C___Tower_Place___Stevedore_Place
  16. Phase_2D___Stevedore_Place___Ocean_Way
  17. Phase_2E___Ocean_Way
  18. Phase_3___Union_Street___London_Road
  19. Phase_4___York_Place___Picardy_Place

Traffic regulation orders

  1. 1._Newhaven___North_Leith_Sands
  2. 2._North_Leith_Sands___Portland_Gardens
  3. 3._PortlandGardens___Ocean_Terminal
  4. 4._Ocean_Terminal___Ocean_Drive
  5. 5._Ocean_Drive___Tower_Place
  6. 6._Tower_Place___Tower_Street
  7. 7._Tower_Street___Queen_Charlotte_Street
  8. 8._Queen_Charlotte_Street___Foot_of_the_Walk
  9. 9._Foot_of_the_Walk___Steads_Place
  10. 10._Steads_Place___Pilrig_Street
  11. 11._Pilrig_Street___Middlefield
  12. 12._Middlefield___McDonald_Road
  13. 13._McDonald_Road___Gayfield_Square
  14. 14._Gayfield_Square___Picardy_Place
  15. A._Island_Tram_Stop
  16. B._Foot_of_the_Walk_Tram_Stop
  17. C._Newhaven_Tram_Stop