Notification of start of construction work (Lindsay Road and Ocean Drive)

(copied from a letter from Trams to Newhaven)

Date 10 February 2020

Dear Sir/Madam,

Notification of start of construction work

Construction works to take trams to Newhaven will commence from Newhaven to Melrose Drive on 6 March 2020 and are scheduled to be completed by Summer 2021. Pedestrian access will be maintained at all times. All parking and loading on Lindsay Road, Melrose Drive and North Leith Sands will be suspended.

Works will also commence on Ocean Drive, at the front of Ocean Terminal, on 13 March 2020, scheduled to be completed by Autumn 2020. Pedestrian access will be maintained at all times. All parking and loading on Ocean Drive and Ocean Way will be suspended. Please note that Ocean Terminal will remain open as usual and access to the car parks will be maintained.

The full construction programme can be viewed on the project website – www.tramstonewhaven.co.uk.

Construction Works
Fencing will be erected in order to establish the construction site which will take approximately two weeks. During this period there will also be further site investigation works undertaken.

Information boards and directional signage will be displayed once the fencing has been erected and the construction site has been established.

Following site set up, Sacyr, Farrans, Neopul (SFN), and Morrison Utility Services (MUS) roles will involve excavation of the road to allow utility diversions, tracklaying, installation of tram infrastructure, public realm improvements, and heritage and archaeology works.

Construction site working hours are Monday to Friday 7am to 7pm and Saturday 8am to 1pm.

Ail works will be undertaken in line with the Code of Construction Practice which details, amongst other things, acceptable levels of noise and vibration. The Code of Construction Practice can be found on the project website – www.tramstonewhaven.co.uk.

Lothian Buses
There will be diversions to your bus services during construction. Full details will be available at www.lothianbuses.com and via the Transport for Edinburgh App.

Bins
There will be no changes to your bin collection arrangements.

Other Works
Other associated work will also be taking place at the following locations:

  1. Foot of the Walk to Coatfield Lane — works are continuing and scheduled to be completed by Spring 2021.
  2. Queen Charlotte Street to Constitution Place — works are continuing and scheduled to be completed by Autumn 2020.
  3. Leith Walk — enabling works are continuing and main construction works will commence 28 March 2020 scheduled to be completed by Summer 2021.

Traffic Management
Traffic management arrangements have been approved jointly with members of the city’s Traffic Management Review Panel, including Lothian Buses and the emergency services, and these will be in place from 6 March 2020 for Newhaven to Melrose Drive and 13 March 2020 for Ocean Drive. Access through the site will be maintained for emergency services at all times. Diversion routes and advanced warning signage will be erected in the vicinity for information and detailed drawings for these can be found on the Trams to Newhaven website.

The project will assess the traffic management arrangement throughout the construction period and make amends where required.

Newsletter
To keep up to date with the project’s progress and news, sign up to our mailing list at www.tramstonewhaven.co.uk.

Considerate Contractor Scheme
SFN and MUS both follow the principles of the Considerate Constructors Scheme, which requires a firm focus on outstanding management, efficiency, awareness of local environmental issues, and a genuine consideration for neighbours and the community.

During the time that the above works are being undertaken, all efforts will be made to minimise disruption and inconvenience to residents and businesses. Further details can be found at
https://www.ccscheme.org.uk/

For further information please visit www.tramstonewhaven.co.uk. Alternatively, you can contact us via email at Newhaven.tram@edinburgh.gov.uk or by phone on 0131 322 1122.

Yours faithfully

Trams to Newhaven Team

Tram Diversion Route Resurfacing Work – Revised Programme

(from an email from Edinburgh Council, time-stamped Wed, 3 Jul 2019 at 15:51)

I write to provide an update to my ongoing carriageway resurfacing programme in and around Leith prior to the commencement of the work to extend the tram to Newhaven.

Works on site at Pilrig Street junction, Dalmeny Street and East London Street are due to complete at the end of next week (Friday 12 July) after which time the main contractor has a company recess for 2 weeks.

On returning to site on the 29 July, the work to redesign the junction at Duke Street and Easter Road will fully commence (some preparatory work will take place next week) while the majority of work ongoing elsewhere will be predominantly carriageway resurfacing work.

To this effect, please find below a basic table detailing the proposed locations, dates and traffic management for the resurfacing work and I have also attached the full programme in the form of a Gantt chart. I will caveat this and remind everyone that dates are approximate as any delays can have a knock on effect, however the order of work should remain the same and I will update EdinTravel as works progress.

I will also explain that the programme has extended due to additional work being requested and some issues on site with traffic signal installations however the main resurfacing work should throw up little in the way of unforeseen delays and there will be no further additional work included in the programme unless it is deemed important and we create space in the existing programme. We also remain in full contact with the team leading the Tram extension with regards their preparatory work and start date.

As before, residents and traders will receive notices prior to the start of work in their area with more specific details, and I will forward a copy of these notices on as appropriate. If you have any queries or concerns, please do not hesitate to contact me.

Month Date (Duration) Location Time Proposed Traffic Management
July 9 (2 days) East London Street Day Road Closure
29 (7 days) North Leith Sands Day Road Closure
29 (35 days) Duke Street R’about Redesign Day Retain roundabout as long as possible
August 7 (5 days) Great Junction Street Day Southbound loop using Henderson?
7 (9 days) Duncan Place Day Road Closure
8 (21 days) Links Place Traffic Islands Day Road Narrowing
15 (4 days) Gordon Street Day Road Closure
20 (3 days) Ocean Drive Day Road Closure.1 side at a time.
20 (12 days) Pilrig Street Day Road Closure in 2 phases
26 (6 days) Annandale Street Day Road Closure
September 2 (12 days) Bonnington Road Night Road Closure in 2 phases
9 (5 days) Broughton Street Night Road Closure
18 (12 days) Newhaven Road Night Road Closure in 2 phases
20 (21 days) Easter Road Night Phased road closures, road narrowing
October 10 (12 days) Broughton Road Night Road Closure in 2 phases
17 (2 days) East Hermitage Pl Junction Night 3 phase TTL’s – Close Links Gdns
28 (5 days) Portland Place Night Eastbound Closure using Ocean Drive
28 (10 days) Links Place Night Road Closure in 2 phases
November 4 (6 days) Academy Street Night Road closure, Duke St eastbound closure

Kind regards

Steven Blacklaw ¦ Engineer – Transport Design & Delivery
Place ¦ Planning & Transport ¦ The City of Edinburgh Council ¦ G4, Waverley Court, 4 East Market Street, Edinburgh EH8 8BG
Tel 0131 529 3252 steven.blacklaw@edinburgh.gov.uk

More detail on carriageway resurfacing works – Summer 2019/20

Following on from this post, Edinburgh Council has just sent the following detail about the road resurfacing planned for this summer.

Location Planned Start Date Estimated Duration Work Detail
Broughton Street 28-May + 22 Aug 4 weeks + 2 weeks Pedestrian crossing upgrade + carriageway resurfacing
Albany Street 03-Jun 1 week Carriageway resurfacing
Hopetoun Street 07-Jun 2 days Carriageway resurfacing
Academy Street 11-Jun 1 week Overlay setts
Dalmeny Street 17-Jun 10 days Carriageway resurfacing, overlay setts and minor footway works
East Hermitage Place 26-Jun 3 days Carriageway resurfacing
Portland Place 28-Jun 1 week Carriageway resurfacing
McDonald Road 01-Jul 10 days Footway widening and carriageway patching
Easter Road/Duke Street 01-Jul 8 weeks Junction redesign
East London Street 02-Jul 7 weeks Pedestrian crossing upgrade and carriageway resurfacing
Duncan Place 10-Jul 2 weeks Carriageway resurfacing and minor footway works
Great Junction Street 10-Jul 1 week Carriageway resurfacing
Gordon Street 02-Aug 1 week Carriageway resurfacing
Bonnington Road 08-Aug 3 weeks Carriageway resurfacing
Ocean Drive 08-Aug 3 days Carriageway resurfacing
North Leith Sands 13-Aug 1 week Carriageway resurfacing and minor footway works
Newhaven Road 26-Aug 2 weeks Carriageway resurfacing
Annandale Street 29-Aug 7 weeks New pedestrian crossings and carriageway resurfacing
Broughton Road 05-Sep 2 weeks Carriageway resurfacing
Easter Road 11-Sep 3 weeks Carriageway resurfacing and minor footway works
Links Place 23-Sep 4 weeks Carriageway resurfacing, new traffic island and footway works
Pilrig Street 29-Sep 4 weeks Carriageway resurfacing, new traffic island and footway works

Proposed Carriageway Resurfacing Works – Summer 2019/20

(adapted from an email from Edinburgh Council)

The carriageway on a number of streets in your Ward are due to be resurfaced during the Summer of 2019. The roads affected have been prioritised because of their current condition and because the upcoming tram works will prevent any planned resurfacing work from taking place in and around the proposed tram line during the construction period.

The resurfacing works are planned to start on 27 May and will be carried out during weekdays in separate phases in order to minimise disruption to the public. On some traffic sensitive routes, work may be carried out under nightshift to minimise the impact on traffic. Most roads affected will be fully or significantly resurfaced with a select few being only partially resurfaced or patched as required. There will also be some improvements to pedestrian facilities, traffic signal upgrades and renewal of some street furniture.

Continue reading

Tram plans

These were downloaded from http://www.edinburgh.gov.uk/tramstonewhaven and are presumably © their creators and/or Edinburgh Council.

Landscape proposals

Traffic management proposals

  1. Phase_1___Albert_Street___Elm_Row
  2. Phase_1___Constitution_Street___Queen_Charlottle_Street
  3. Phase_1___Constitution_Street___Steads_Place
  4. Phase_1___Newhaven___North_Leith_Sands
  5. Phase_1___North_Leith_Sands_to_Ocean_Terminal_Southside
  6. Phase_1___Ocean_Terminal_Southside
  7. Phase_1___Ocean_Terminal
  8. Phase_1___Steads_Place___Albert_Street
  9. Phase_2___Foot_of_the_Walk_to_Manderston_Street
  10. Phase_2___Ocean_Drive___Tower_Place
  11. Phase_2___Ocean_Terminal___Ocean_Drive
  12. Phase_2___Picardy_Place___Union_Street
  13. Phase_2A___Queen_Charlottle_Street___Coatfield_Lane
  14. Phase_2B___Stevedore_Place___Constitution_Street
  15. Phase_2C___Tower_Place___Stevedore_Place
  16. Phase_2D___Stevedore_Place___Ocean_Way
  17. Phase_2E___Ocean_Way
  18. Phase_3___Union_Street___London_Road
  19. Phase_4___York_Place___Picardy_Place

Traffic regulation orders

  1. 1._Newhaven___North_Leith_Sands
  2. 2._North_Leith_Sands___Portland_Gardens
  3. 3._PortlandGardens___Ocean_Terminal
  4. 4._Ocean_Terminal___Ocean_Drive
  5. 5._Ocean_Drive___Tower_Place
  6. 6._Tower_Place___Tower_Street
  7. 7._Tower_Street___Queen_Charlotte_Street
  8. 8._Queen_Charlotte_Street___Foot_of_the_Walk
  9. 9._Foot_of_the_Walk___Steads_Place
  10. 10._Steads_Place___Pilrig_Street
  11. 11._Pilrig_Street___Middlefield
  12. 12._Middlefield___McDonald_Road
  13. 13._McDonald_Road___Gayfield_Square
  14. 14._Gayfield_Square___Picardy_Place
  15. A._Island_Tram_Stop
  16. B._Foot_of_the_Walk_Tram_Stop
  17. C._Newhaven_Tram_Stop