Constitution Street tram-construction start

(adapted from an email from the Trams to Newhaven project.)

The Tram to Newhaven project team is hosting a drop-in event on Thursday 7 November from 12pm – 7.30pm at South Leith Parish Church where residents and businesses can come and meet the team who can answer any queries they might have about the planned works.

The first phase of work to take trams to Newhaven will start on Constitution Street on 18 November 2019. Continue reading

Public utility works: Leith Area

(adapted from an email from Graham Hall (CEC Senior Transport Team Leader) to Leith ward and Leith Walk ward councillors; with thanks to the councillor that forwarded it to community councils. This information reached LHNCC’s webmaster today [19 July].)

As you will be no doubt aware, The City of Edinburgh Council is carrying out significant pre-tram surfacing works in wards 12 and 13 at the current time via our Transport Design and Delivery section who have McLay’s Ltd carrying out numerous projects in preparation for the Tram extension works which are due to commence later this year.

In addition to these works City Fibre have started their programme to install fibre to the home in the area as well as the other utility providers continuing their business as usual.

It has been agreed with the CEC project manager (Steven Blacklaw) that the locality will coordinate these works around his significant programme to avoid conflict with different sets of work. As McLays Ltd are based in Airdrie and traditionally close down for the Glasgow Fayre fortnight commencing on the 12th of July I have delayed various utility works commencing until McLay’s have closed their sites down and to prevent additional pressure on the road network. The works below have been approved for the period 14th July 2019 to 30 July 2019 to avoid any conflict with the CEC programme.

Whilst there will no doubt be some form of delay caused by the various works, please be assured that every effort has been made to minimise disruption utilising the quieter school holiday period whilst still ensuring these works are completed before CEC’s contractor returns to recommence his programme. Please also note that where required, any works which may present significant disruption have been discussed and approved at the City Wide Traffic Management Group to ensure the most effective traffic management is employed.

Should you have any further questions please do not hesitate to call on the number below.

Utility Location Nature of works Works Start Finish Traffic Management
City Fibre Salamander Street Installing new fibre optic cable TBC TBC Two way temporary traffic signals
City Fibre East Hermitage Place Installing new fibre optic cable 14/07/2019 17/07/2019 Three way temporary traffic signals
Scottish Power Albert Street Main Cable repair 15/07/2019 19/07/2019 Parking Restriction only
Scottish Power Constitution Street Install new service 19/07/2019 23/07/2019 Parking Restriction only
Scottish Power Pilrig Street at Dryden Street Excavate footway to replace joint TBC TBC Parking Restriction only
Scottish Gas Networks Newhaven Road at Graham Street Install new connection to gas main 14/07/2019 30/07/2019 Three way temporary traffic signals
Scottish Gas Networks North Junction Street at Ferry Road Replace existing gas main 14/07/2019 30/07/2019 Three way temporary traffic signals
Virgin Media Lindsay Road at Sandpiper Drive Install new service 15/07/2019 19/07/2019 Lane restrictions and local diversion

Graham Hall – FIHE – Senior Transport Team Leader – Place – City of Edinburgh Council – North East Locality, 101 Niddrie Mains Rd, Edinburgh, EH16 4DS – Tel: 0131 469 3926 – Northeast.transport@edinburgh.gov.uk

Please note: all correspondence should be sent to Northeast.transport@edinburgh.gov.uk

Tram Diversion Route Resurfacing Work – Revised Programme

(from an email from Edinburgh Council, time-stamped Wed, 3 Jul 2019 at 15:51)

I write to provide an update to my ongoing carriageway resurfacing programme in and around Leith prior to the commencement of the work to extend the tram to Newhaven.

Works on site at Pilrig Street junction, Dalmeny Street and East London Street are due to complete at the end of next week (Friday 12 July) after which time the main contractor has a company recess for 2 weeks.

On returning to site on the 29 July, the work to redesign the junction at Duke Street and Easter Road will fully commence (some preparatory work will take place next week) while the majority of work ongoing elsewhere will be predominantly carriageway resurfacing work.

To this effect, please find below a basic table detailing the proposed locations, dates and traffic management for the resurfacing work and I have also attached the full programme in the form of a Gantt chart. I will caveat this and remind everyone that dates are approximate as any delays can have a knock on effect, however the order of work should remain the same and I will update EdinTravel as works progress.

I will also explain that the programme has extended due to additional work being requested and some issues on site with traffic signal installations however the main resurfacing work should throw up little in the way of unforeseen delays and there will be no further additional work included in the programme unless it is deemed important and we create space in the existing programme. We also remain in full contact with the team leading the Tram extension with regards their preparatory work and start date.

As before, residents and traders will receive notices prior to the start of work in their area with more specific details, and I will forward a copy of these notices on as appropriate. If you have any queries or concerns, please do not hesitate to contact me.

Month Date (Duration) Location Time Proposed Traffic Management
July 9 (2 days) East London Street Day Road Closure
29 (7 days) North Leith Sands Day Road Closure
29 (35 days) Duke Street R’about Redesign Day Retain roundabout as long as possible
August 7 (5 days) Great Junction Street Day Southbound loop using Henderson?
7 (9 days) Duncan Place Day Road Closure
8 (21 days) Links Place Traffic Islands Day Road Narrowing
15 (4 days) Gordon Street Day Road Closure
20 (3 days) Ocean Drive Day Road Closure.1 side at a time.
20 (12 days) Pilrig Street Day Road Closure in 2 phases
26 (6 days) Annandale Street Day Road Closure
September 2 (12 days) Bonnington Road Night Road Closure in 2 phases
9 (5 days) Broughton Street Night Road Closure
18 (12 days) Newhaven Road Night Road Closure in 2 phases
20 (21 days) Easter Road Night Phased road closures, road narrowing
October 10 (12 days) Broughton Road Night Road Closure in 2 phases
17 (2 days) East Hermitage Pl Junction Night 3 phase TTL’s – Close Links Gdns
28 (5 days) Portland Place Night Eastbound Closure using Ocean Drive
28 (10 days) Links Place Night Road Closure in 2 phases
November 4 (6 days) Academy Street Night Road closure, Duke St eastbound closure

Kind regards

Steven Blacklaw ¦ Engineer – Transport Design & Delivery
Place ¦ Planning & Transport ¦ The City of Edinburgh Council ¦ G4, Waverley Court, 4 East Market Street, Edinburgh EH8 8BG
Tel 0131 529 3252 steven.blacklaw@edinburgh.gov.uk

More detail on carriageway resurfacing works – Summer 2019/20

Following on from this post, Edinburgh Council has just sent the following detail about the road resurfacing planned for this summer.

Location Planned Start Date Estimated Duration Work Detail
Broughton Street 28-May + 22 Aug 4 weeks + 2 weeks Pedestrian crossing upgrade + carriageway resurfacing
Albany Street 03-Jun 1 week Carriageway resurfacing
Hopetoun Street 07-Jun 2 days Carriageway resurfacing
Academy Street 11-Jun 1 week Overlay setts
Dalmeny Street 17-Jun 10 days Carriageway resurfacing, overlay setts and minor footway works
East Hermitage Place 26-Jun 3 days Carriageway resurfacing
Portland Place 28-Jun 1 week Carriageway resurfacing
McDonald Road 01-Jul 10 days Footway widening and carriageway patching
Easter Road/Duke Street 01-Jul 8 weeks Junction redesign
East London Street 02-Jul 7 weeks Pedestrian crossing upgrade and carriageway resurfacing
Duncan Place 10-Jul 2 weeks Carriageway resurfacing and minor footway works
Great Junction Street 10-Jul 1 week Carriageway resurfacing
Gordon Street 02-Aug 1 week Carriageway resurfacing
Bonnington Road 08-Aug 3 weeks Carriageway resurfacing
Ocean Drive 08-Aug 3 days Carriageway resurfacing
North Leith Sands 13-Aug 1 week Carriageway resurfacing and minor footway works
Newhaven Road 26-Aug 2 weeks Carriageway resurfacing
Annandale Street 29-Aug 7 weeks New pedestrian crossings and carriageway resurfacing
Broughton Road 05-Sep 2 weeks Carriageway resurfacing
Easter Road 11-Sep 3 weeks Carriageway resurfacing and minor footway works
Links Place 23-Sep 4 weeks Carriageway resurfacing, new traffic island and footway works
Pilrig Street 29-Sep 4 weeks Carriageway resurfacing, new traffic island and footway works