Notification of start of construction work (Lindsay Road and Ocean Drive)

(copied from a letter from Trams to Newhaven)

Date 10 February 2020

Dear Sir/Madam,

Notification of start of construction work

Construction works to take trams to Newhaven will commence from Newhaven to Melrose Drive on 6 March 2020 and are scheduled to be completed by Summer 2021. Pedestrian access will be maintained at all times. All parking and loading on Lindsay Road, Melrose Drive and North Leith Sands will be suspended.

Works will also commence on Ocean Drive, at the front of Ocean Terminal, on 13 March 2020, scheduled to be completed by Autumn 2020. Pedestrian access will be maintained at all times. All parking and loading on Ocean Drive and Ocean Way will be suspended. Please note that Ocean Terminal will remain open as usual and access to the car parks will be maintained.

The full construction programme can be viewed on the project website – www.tramstonewhaven.co.uk.

Construction Works
Fencing will be erected in order to establish the construction site which will take approximately two weeks. During this period there will also be further site investigation works undertaken.

Information boards and directional signage will be displayed once the fencing has been erected and the construction site has been established.

Following site set up, Sacyr, Farrans, Neopul (SFN), and Morrison Utility Services (MUS) roles will involve excavation of the road to allow utility diversions, tracklaying, installation of tram infrastructure, public realm improvements, and heritage and archaeology works.

Construction site working hours are Monday to Friday 7am to 7pm and Saturday 8am to 1pm.

Ail works will be undertaken in line with the Code of Construction Practice which details, amongst other things, acceptable levels of noise and vibration. The Code of Construction Practice can be found on the project website – www.tramstonewhaven.co.uk.

Lothian Buses
There will be diversions to your bus services during construction. Full details will be available at www.lothianbuses.com and via the Transport for Edinburgh App.

Bins
There will be no changes to your bin collection arrangements.

Other Works
Other associated work will also be taking place at the following locations:

  1. Foot of the Walk to Coatfield Lane — works are continuing and scheduled to be completed by Spring 2021.
  2. Queen Charlotte Street to Constitution Place — works are continuing and scheduled to be completed by Autumn 2020.
  3. Leith Walk — enabling works are continuing and main construction works will commence 28 March 2020 scheduled to be completed by Summer 2021.

Traffic Management
Traffic management arrangements have been approved jointly with members of the city’s Traffic Management Review Panel, including Lothian Buses and the emergency services, and these will be in place from 6 March 2020 for Newhaven to Melrose Drive and 13 March 2020 for Ocean Drive. Access through the site will be maintained for emergency services at all times. Diversion routes and advanced warning signage will be erected in the vicinity for information and detailed drawings for these can be found on the Trams to Newhaven website.

The project will assess the traffic management arrangement throughout the construction period and make amends where required.

Newsletter
To keep up to date with the project’s progress and news, sign up to our mailing list at www.tramstonewhaven.co.uk.

Considerate Contractor Scheme
SFN and MUS both follow the principles of the Considerate Constructors Scheme, which requires a firm focus on outstanding management, efficiency, awareness of local environmental issues, and a genuine consideration for neighbours and the community.

During the time that the above works are being undertaken, all efforts will be made to minimise disruption and inconvenience to residents and businesses. Further details can be found at
https://www.ccscheme.org.uk/

For further information please visit www.tramstonewhaven.co.uk. Alternatively, you can contact us via email at Newhaven.tram@edinburgh.gov.uk or by phone on 0131 322 1122.

Yours faithfully

Trams to Newhaven Team

Tram plans

These were downloaded from http://www.edinburgh.gov.uk/tramstonewhaven and are presumably © their creators and/or Edinburgh Council.

Landscape proposals

Traffic management proposals

  1. Phase_1___Albert_Street___Elm_Row
  2. Phase_1___Constitution_Street___Queen_Charlottle_Street
  3. Phase_1___Constitution_Street___Steads_Place
  4. Phase_1___Newhaven___North_Leith_Sands
  5. Phase_1___North_Leith_Sands_to_Ocean_Terminal_Southside
  6. Phase_1___Ocean_Terminal_Southside
  7. Phase_1___Ocean_Terminal
  8. Phase_1___Steads_Place___Albert_Street
  9. Phase_2___Foot_of_the_Walk_to_Manderston_Street
  10. Phase_2___Ocean_Drive___Tower_Place
  11. Phase_2___Ocean_Terminal___Ocean_Drive
  12. Phase_2___Picardy_Place___Union_Street
  13. Phase_2A___Queen_Charlottle_Street___Coatfield_Lane
  14. Phase_2B___Stevedore_Place___Constitution_Street
  15. Phase_2C___Tower_Place___Stevedore_Place
  16. Phase_2D___Stevedore_Place___Ocean_Way
  17. Phase_2E___Ocean_Way
  18. Phase_3___Union_Street___London_Road
  19. Phase_4___York_Place___Picardy_Place

Traffic regulation orders

  1. 1._Newhaven___North_Leith_Sands
  2. 2._North_Leith_Sands___Portland_Gardens
  3. 3._PortlandGardens___Ocean_Terminal
  4. 4._Ocean_Terminal___Ocean_Drive
  5. 5._Ocean_Drive___Tower_Place
  6. 6._Tower_Place___Tower_Street
  7. 7._Tower_Street___Queen_Charlotte_Street
  8. 8._Queen_Charlotte_Street___Foot_of_the_Walk
  9. 9._Foot_of_the_Walk___Steads_Place
  10. 10._Steads_Place___Pilrig_Street
  11. 11._Pilrig_Street___Middlefield
  12. 12._Middlefield___McDonald_Road
  13. 13._McDonald_Road___Gayfield_Square
  14. 14._Gayfield_Square___Picardy_Place
  15. A._Island_Tram_Stop
  16. B._Foot_of_the_Walk_Tram_Stop
  17. C._Newhaven_Tram_Stop

 

 

 

 

 

LHNCC January 2018 minutes

Minutes of the Leith Harbour and Newhaven Community Council meeting, held at Leith Community Centre on Tuesday 23 January 2018 at 7.00pm

Continue reading