Community Councils Together on Trams/Trams Team meeting, 27 February 2020

Minutes of the Community Councils Together on Trams/Trams Team meeting (No 2 Construction Phase) at 165 Leith Walk on Thursday 27 February at 5:30pm Continue reading

Notification of start of construction work (Lindsay Road and Ocean Drive)

(copied from a letter from Trams to Newhaven)

Date 10 February 2020

Dear Sir/Madam,

Notification of start of construction work

Construction works to take trams to Newhaven will commence from Newhaven to Melrose Drive on 6 March 2020 and are scheduled to be completed by Summer 2021. Pedestrian access will be maintained at all times. All parking and loading on Lindsay Road, Melrose Drive and North Leith Sands will be suspended.

Works will also commence on Ocean Drive, at the front of Ocean Terminal, on 13 March 2020, scheduled to be completed by Autumn 2020. Pedestrian access will be maintained at all times. All parking and loading on Ocean Drive and Ocean Way will be suspended. Please note that Ocean Terminal will remain open as usual and access to the car parks will be maintained.

The full construction programme can be viewed on the project website – www.tramstonewhaven.co.uk.

Construction Works
Fencing will be erected in order to establish the construction site which will take approximately two weeks. During this period there will also be further site investigation works undertaken.

Information boards and directional signage will be displayed once the fencing has been erected and the construction site has been established.

Following site set up, Sacyr, Farrans, Neopul (SFN), and Morrison Utility Services (MUS) roles will involve excavation of the road to allow utility diversions, tracklaying, installation of tram infrastructure, public realm improvements, and heritage and archaeology works.

Construction site working hours are Monday to Friday 7am to 7pm and Saturday 8am to 1pm.

Ail works will be undertaken in line with the Code of Construction Practice which details, amongst other things, acceptable levels of noise and vibration. The Code of Construction Practice can be found on the project website – www.tramstonewhaven.co.uk.

Lothian Buses
There will be diversions to your bus services during construction. Full details will be available at www.lothianbuses.com and via the Transport for Edinburgh App.

Bins
There will be no changes to your bin collection arrangements.

Other Works
Other associated work will also be taking place at the following locations:

  1. Foot of the Walk to Coatfield Lane — works are continuing and scheduled to be completed by Spring 2021.
  2. Queen Charlotte Street to Constitution Place — works are continuing and scheduled to be completed by Autumn 2020.
  3. Leith Walk — enabling works are continuing and main construction works will commence 28 March 2020 scheduled to be completed by Summer 2021.

Traffic Management
Traffic management arrangements have been approved jointly with members of the city’s Traffic Management Review Panel, including Lothian Buses and the emergency services, and these will be in place from 6 March 2020 for Newhaven to Melrose Drive and 13 March 2020 for Ocean Drive. Access through the site will be maintained for emergency services at all times. Diversion routes and advanced warning signage will be erected in the vicinity for information and detailed drawings for these can be found on the Trams to Newhaven website.

The project will assess the traffic management arrangement throughout the construction period and make amends where required.

Newsletter
To keep up to date with the project’s progress and news, sign up to our mailing list at www.tramstonewhaven.co.uk.

Considerate Contractor Scheme
SFN and MUS both follow the principles of the Considerate Constructors Scheme, which requires a firm focus on outstanding management, efficiency, awareness of local environmental issues, and a genuine consideration for neighbours and the community.

During the time that the above works are being undertaken, all efforts will be made to minimise disruption and inconvenience to residents and businesses. Further details can be found at
https://www.ccscheme.org.uk/

For further information please visit www.tramstonewhaven.co.uk. Alternatively, you can contact us via email at Newhaven.tram@edinburgh.gov.uk or by phone on 0131 322 1122.

Yours faithfully

Trams to Newhaven Team

Proposed Carriageway Resurfacing Works – Summer 2019/20

(adapted from an email from Edinburgh Council)

The carriageway on a number of streets in your Ward are due to be resurfaced during the Summer of 2019. The roads affected have been prioritised because of their current condition and because the upcoming tram works will prevent any planned resurfacing work from taking place in and around the proposed tram line during the construction period.

The resurfacing works are planned to start on 27 May and will be carried out during weekdays in separate phases in order to minimise disruption to the public. On some traffic sensitive routes, work may be carried out under nightshift to minimise the impact on traffic. Most roads affected will be fully or significantly resurfaced with a select few being only partially resurfaced or patched as required. There will also be some improvements to pedestrian facilities, traffic signal upgrades and renewal of some street furniture.

Continue reading

LHNCC minutes: March 2019

Minutes of the Leith Harbour and Newhaven Community Council ordinary meeting, held at Leith Community Centre on Tuesday 26 March 2019 at 6.30pm

Actions and decisions are red italic. Nem con means that no-one spoke or voted against an item. Continue reading

LHNCC minutes: October 2018

Minutes of the Leith Harbour and Newhaven Community Council ordinary meeting, held at Leith Community Centre on Tuesday 23 October 2018 at 6.30pm

Actions and decisions are red italic. Nem con means that no-one spoke or voted against an item. Continue reading

LHNCC minutes: April 2018

Minutes of the Leith Harbour and Newhaven Community Council meeting, held at Leith Community Centre on Tuesday 24 April 2018 at 7.00pm

Actions and decisions are red italic underlined. Nem con means that no-one spoke or voted against an item. Continue reading