Easter Rd
Newhaven Tram project update
(adapted form an email from ‘Trams to Newhaven’)
Leith Walk Planters
In order to facilitate construction of Trams to Newhaven project, the 14 planters that are currently situated on Leith Walk will be moved to the Leith Links / Duke Street / Lochend Road / Easter Road junction. This will be a permanent move in order to accommodate dedicated cycling lanes post construction. The planters will be moved as part of the enabling works commencing on Monday 18 November 2019.
We are aware that some businesses / residents have been looking after the planters and where this is known we have made contact to explain. An example of this is the Kadampa Meditation Centre who we visited to explain what is happening and to thank them for the work they have done. We will be attaching posters to the planters this week to highlight the planters being moved.
Trimming of trees at South Leith Parish Church Wall
In order to begin works on the South Leith Parish Church wall later in December 2019, TD Tree and Land Services Limited, a specialist in tree maintenance, will trim back overhanging branches in order to gain access to the wall. The works will take place over two days (Monday 18 and Tuesday 19 November) and will not damage the trees in any way.
Wherever possible all work will be carried out from the ground. If required, trees will be climbed by trained personnel and will only take place once an assessment has been made that is safe to do so.
An eco-check for bats and nesting birds was undertaken recently which identified the trees had not been used by either species.
We will be highlighting both of above on the project website and in the electronic newsletter this week.
Tram Diversion Route Resurfacing Work – Revised Programme
(from an email from Edinburgh Council, time-stamped Wed, 3 Jul 2019 at 15:51)
I write to provide an update to my ongoing carriageway resurfacing programme in and around Leith prior to the commencement of the work to extend the tram to Newhaven.
Works on site at Pilrig Street junction, Dalmeny Street and East London Street are due to complete at the end of next week (Friday 12 July) after which time the main contractor has a company recess for 2 weeks.
On returning to site on the 29 July, the work to redesign the junction at Duke Street and Easter Road will fully commence (some preparatory work will take place next week) while the majority of work ongoing elsewhere will be predominantly carriageway resurfacing work.
To this effect, please find below a basic table detailing the proposed locations, dates and traffic management for the resurfacing work and I have also attached the full programme in the form of a Gantt chart. I will caveat this and remind everyone that dates are approximate as any delays can have a knock on effect, however the order of work should remain the same and I will update EdinTravel as works progress.
I will also explain that the programme has extended due to additional work being requested and some issues on site with traffic signal installations however the main resurfacing work should throw up little in the way of unforeseen delays and there will be no further additional work included in the programme unless it is deemed important and we create space in the existing programme. We also remain in full contact with the team leading the Tram extension with regards their preparatory work and start date.
As before, residents and traders will receive notices prior to the start of work in their area with more specific details, and I will forward a copy of these notices on as appropriate. If you have any queries or concerns, please do not hesitate to contact me.
| Month | Date (Duration) | Location | Time | Proposed Traffic Management |
| July | 9 (2 days) | East London Street | Day | Road Closure |
| 29 (7 days) | North Leith Sands | Day | Road Closure | |
| 29 (35 days) | Duke Street R’about Redesign | Day | Retain roundabout as long as possible | |
| August | 7 (5 days) | Great Junction Street | Day | Southbound loop using Henderson? |
| 7 (9 days) | Duncan Place | Day | Road Closure | |
| 8 (21 days) | Links Place Traffic Islands | Day | Road Narrowing | |
| 15 (4 days) | Gordon Street | Day | Road Closure | |
| 20 (3 days) | Ocean Drive | Day | Road Closure.1 side at a time. | |
| 20 (12 days) | Pilrig Street | Day | Road Closure in 2 phases | |
| 26 (6 days) | Annandale Street | Day | Road Closure | |
| September | 2 (12 days) | Bonnington Road | Night | Road Closure in 2 phases |
| 9 (5 days) | Broughton Street | Night | Road Closure | |
| 18 (12 days) | Newhaven Road | Night | Road Closure in 2 phases | |
| 20 (21 days) | Easter Road | Night | Phased road closures, road narrowing | |
| October | 10 (12 days) | Broughton Road | Night | Road Closure in 2 phases |
| 17 (2 days) | East Hermitage Pl Junction | Night | 3 phase TTL’s – Close Links Gdns | |
| 28 (5 days) | Portland Place | Night | Eastbound Closure using Ocean Drive | |
| 28 (10 days) | Links Place | Night | Road Closure in 2 phases | |
| November | 4 (6 days) | Academy Street | Night | Road closure, Duke St eastbound closure |
Kind regards
Steven Blacklaw ¦ Engineer – Transport Design & Delivery
Place ¦ Planning & Transport ¦ The City of Edinburgh Council ¦ G4, Waverley Court, 4 East Market Street, Edinburgh EH8 8BG
Tel 0131 529 3252 steven.blacklaw@edinburgh.gov.uk
Minutes of the Community Councils Together on Trams/Trams Team meeting, held at 200 Bonnington Road on Wednesday 6 June 2019 at 5:30pm
Actions and decisions are red italic.
1 Abbreviations
| BAFO = best and final offer | LLCC = Leith Links Community Council |
| CCTT = Community Councils Together on Trams | LW = Leith Walk |
| CEC = City of Edinburgh Council | NTBCC = New Town & Broughton Community Council |
| CPZ = controlled parking zone | OBC = outline business case |
| CS = Constitution St | POLHA = Port of Leith Housing Association |
| ECI = early contractor involvement | SPC = swept-path contract |
| EIA = environmental impact assessment | TAPOG = CEC’s tram all-party oversight group |
| FBC = full business case | TfE = Transport for Edinburgh |
| ISC = infrastructure and systems contract | TN = Trams to Newhaven project |
| LCCC = Leith Central Community Council | TRO = traffic regulation order |
| LHNCC = Leith Harbour & Newhaven Community Council | TT = trams team |
TAPOG is CEC’s leader and vice-leader, CEC’s transport convenor and vice-convenor, and transport spokespersons from each party Continue reading
More detail on carriageway resurfacing works – Summer 2019/20
Following on from this post, Edinburgh Council has just sent the following detail about the road resurfacing planned for this summer.
| Location | Planned Start Date | Estimated Duration | Work Detail |
| Broughton Street | 28-May + 22 Aug | 4 weeks + 2 weeks | Pedestrian crossing upgrade + carriageway resurfacing |
| Albany Street | 03-Jun | 1 week | Carriageway resurfacing |
| Hopetoun Street | 07-Jun | 2 days | Carriageway resurfacing |
| Academy Street | 11-Jun | 1 week | Overlay setts |
| Dalmeny Street | 17-Jun | 10 days | Carriageway resurfacing, overlay setts and minor footway works |
| East Hermitage Place | 26-Jun | 3 days | Carriageway resurfacing |
| Portland Place | 28-Jun | 1 week | Carriageway resurfacing |
| McDonald Road | 01-Jul | 10 days | Footway widening and carriageway patching |
| Easter Road/Duke Street | 01-Jul | 8 weeks | Junction redesign |
| East London Street | 02-Jul | 7 weeks | Pedestrian crossing upgrade and carriageway resurfacing |
| Duncan Place | 10-Jul | 2 weeks | Carriageway resurfacing and minor footway works |
| Great Junction Street | 10-Jul | 1 week | Carriageway resurfacing |
| Gordon Street | 02-Aug | 1 week | Carriageway resurfacing |
| Bonnington Road | 08-Aug | 3 weeks | Carriageway resurfacing |
| Ocean Drive | 08-Aug | 3 days | Carriageway resurfacing |
| North Leith Sands | 13-Aug | 1 week | Carriageway resurfacing and minor footway works |
| Newhaven Road | 26-Aug | 2 weeks | Carriageway resurfacing |
| Annandale Street | 29-Aug | 7 weeks | New pedestrian crossings and carriageway resurfacing |
| Broughton Road | 05-Sep | 2 weeks | Carriageway resurfacing |
| Easter Road | 11-Sep | 3 weeks | Carriageway resurfacing and minor footway works |
| Links Place | 23-Sep | 4 weeks | Carriageway resurfacing, new traffic island and footway works |
| Pilrig Street | 29-Sep | 4 weeks | Carriageway resurfacing, new traffic island and footway works |
Proposed Carriageway Resurfacing Works – Summer 2019/20
(adapted from an email from Edinburgh Council)
The carriageway on a number of streets in your Ward are due to be resurfaced during the Summer of 2019. The roads affected have been prioritised because of their current condition and because the upcoming tram works will prevent any planned resurfacing work from taking place in and around the proposed tram line during the construction period.
The resurfacing works are planned to start on 27 May and will be carried out during weekdays in separate phases in order to minimise disruption to the public. On some traffic sensitive routes, work may be carried out under nightshift to minimise the impact on traffic. Most roads affected will be fully or significantly resurfaced with a select few being only partially resurfaced or patched as required. There will also be some improvements to pedestrian facilities, traffic signal upgrades and renewal of some street furniture.
Community Councils Together on Trams/Trams Team meeting, Thursday 30 January 2019
Minutes of the Community Councils Together on Trams/Trams Team meeting, held in Leith Community Education Centre on Thursday 30 January 2019 at 5:30pm
Actions and decisions are red italic. Continue reading