Community Councils Together on Trams/Trams Team meeting, 29 April 2021

**attempt 2 to post this legibly. If this doesn’t help, here’s a PDF of the original Word document**

Minutes of the Community Councils Together on Trams/Trams Team meeting
(Construction Phase) via Google Meet on Thursday 29 April 2021 at 5:30pm Continue reading

Community Councils Together on Trams/Trams Team meeting, 29 April 2021

Minutes of the Community Councils Together on Trams/Trams Team meeting
(Construction Phase) via Google Meet on Thursday 29 April 2021 at 5:30pm Continue reading

Community Councils Together on Trams/Trams Team meeting, 27 August 2020

Minutes of the Community Councils Together on Trams/Trams Team meeting (Construction Phase) via Google Meet on Thursday 27 August 2020 at 5:30pm Continue reading

Community Councils Together on Trams/Trams Team meeting, 30 July 2020

Minutes of the Community Councils Together on Trams/Trams Team meeting (Construction Phase) via Google Meet on Thursday 30 July 2020 at 5:30pm Continue reading

Proposed waiting/loading restriction changes to facilitate footway widening – Great Junction Street

Copied from an email from CEC’s Spaces for People

Covid-19 Cycling and Walking Emergency Response Measures

Proposed waiting/loading restriction changes to facilitate footway widening – Great Junction Street

Following our email of 26 June advising that we would notify you once further details were available for the proposals above, we are pleased to be able to provide these now. We are aware that you were initially given proposals for Great Junction Street and Easter Road in a single notification, however in an effort to provide details at the earliest opportunity these have been separated and plans for Easter Road will be issued as soon as they are available.

We would suggest that you view the plan to see the detail of what is proposed.

map of proposals for Great Junction St and Easter Rd

Click the graphic to see the full PDF. LHNCC’s web-weaver is not happy that the map does not include a key.

Continue reading

Community Councils Together on Trams/Trams Team meeting, 25 June 2020

Minutes of the Community Councils Together on Trams/Trams Team meeting
(Construction Phase) via Google Meet on Thursday 25 June 2020 at 5:30pm Continue reading

Community Councils Together on Trams/Trams Team meeting, 27 February 2020

Minutes of the Community Councils Together on Trams/Trams Team meeting (No 2 Construction Phase) at 165 Leith Walk on Thursday 27 February at 5:30pm Continue reading

Newhaven Tram project update

(adapted form an email from ‘Trams to Newhaven’)

Leith Walk Planters

In order to facilitate construction of Trams to Newhaven project, the 14 planters that are currently situated on Leith Walk will be moved to the Leith Links / Duke Street / Lochend Road / Easter Road junction. This will be a permanent move in order to accommodate dedicated cycling lanes post construction. The planters will be moved as part of the enabling works commencing on Monday 18 November 2019.

We are aware that some businesses / residents have been looking after the planters and where this is known we have made contact to explain. An example of this is the Kadampa Meditation Centre who we visited to explain what is happening and to thank them for the work they have done. We will be attaching posters to the planters this week to highlight the planters being moved.

Trimming of trees at South Leith Parish Church Wall

In order to begin works on the South Leith Parish Church wall later in December 2019, TD Tree and Land Services Limited, a specialist in tree maintenance, will trim back overhanging branches in order to gain access to the wall. The works will take place over two days (Monday 18 and Tuesday 19 November) and will not damage the trees in any way.

Wherever possible all work will be carried out from the ground.  If required, trees will be climbed by trained personnel and will only take place once an assessment has been made that is safe to do so.

An eco-check for bats and nesting birds was undertaken recently which identified the trees had not been used by either species.

We will be highlighting both of above on the project website and in the electronic newsletter this week.

Tram Diversion Route Resurfacing Work – Revised Programme

(from an email from Edinburgh Council, time-stamped Wed, 3 Jul 2019 at 15:51)

I write to provide an update to my ongoing carriageway resurfacing programme in and around Leith prior to the commencement of the work to extend the tram to Newhaven.

Works on site at Pilrig Street junction, Dalmeny Street and East London Street are due to complete at the end of next week (Friday 12 July) after which time the main contractor has a company recess for 2 weeks.

On returning to site on the 29 July, the work to redesign the junction at Duke Street and Easter Road will fully commence (some preparatory work will take place next week) while the majority of work ongoing elsewhere will be predominantly carriageway resurfacing work.

To this effect, please find below a basic table detailing the proposed locations, dates and traffic management for the resurfacing work and I have also attached the full programme in the form of a Gantt chart. I will caveat this and remind everyone that dates are approximate as any delays can have a knock on effect, however the order of work should remain the same and I will update EdinTravel as works progress.

I will also explain that the programme has extended due to additional work being requested and some issues on site with traffic signal installations however the main resurfacing work should throw up little in the way of unforeseen delays and there will be no further additional work included in the programme unless it is deemed important and we create space in the existing programme. We also remain in full contact with the team leading the Tram extension with regards their preparatory work and start date.

As before, residents and traders will receive notices prior to the start of work in their area with more specific details, and I will forward a copy of these notices on as appropriate. If you have any queries or concerns, please do not hesitate to contact me.

Month Date (Duration) Location Time Proposed Traffic Management
July 9 (2 days) East London Street Day Road Closure
29 (7 days) North Leith Sands Day Road Closure
29 (35 days) Duke Street R’about Redesign Day Retain roundabout as long as possible
August 7 (5 days) Great Junction Street Day Southbound loop using Henderson?
7 (9 days) Duncan Place Day Road Closure
8 (21 days) Links Place Traffic Islands Day Road Narrowing
15 (4 days) Gordon Street Day Road Closure
20 (3 days) Ocean Drive Day Road Closure.1 side at a time.
20 (12 days) Pilrig Street Day Road Closure in 2 phases
26 (6 days) Annandale Street Day Road Closure
September 2 (12 days) Bonnington Road Night Road Closure in 2 phases
9 (5 days) Broughton Street Night Road Closure
18 (12 days) Newhaven Road Night Road Closure in 2 phases
20 (21 days) Easter Road Night Phased road closures, road narrowing
October 10 (12 days) Broughton Road Night Road Closure in 2 phases
17 (2 days) East Hermitage Pl Junction Night 3 phase TTL’s – Close Links Gdns
28 (5 days) Portland Place Night Eastbound Closure using Ocean Drive
28 (10 days) Links Place Night Road Closure in 2 phases
November 4 (6 days) Academy Street Night Road closure, Duke St eastbound closure

Kind regards

Steven Blacklaw ¦ Engineer – Transport Design & Delivery
Place ¦ Planning & Transport ¦ The City of Edinburgh Council ¦ G4, Waverley Court, 4 East Market Street, Edinburgh EH8 8BG
Tel 0131 529 3252 steven.blacklaw@edinburgh.gov.uk