Community Councils Together on Trams/Trams Team meeting, 12 December 2022

Minutes of the Community Councils Together on Trams/Trams Team meeting on Thursday 12 December 2022 at 5pm, at Trams project compound (165 Leith Walk)

Actions and decisions are red italic. ‘TT’ means ‘Trams Team’. Names are mostly abbreviated to initials.

[text in square brackets] is glosses, i.e. implications unspoken at this point but drawn from other spoken items. Continue reading

Annandale Street to Picardy Place southbound road closure

LHNCC’s web weaver apologies for not also posting this on LHNCC’s website when it was first supplied.

On 24 October 2022, there will be changes to the traffic management arrangements on the southbound section of Leith Walk between Annandale Street and Picardy Place to allow final surfacing and lining works to take place.

This will involve a closure of the southbound carriageway for approximately three weeks from Annandale Street to the Picardy Place turnback, including the full junction at London Road. The Picardy Place turnback will remain operational throughout the duration of these works. Continue reading

Community Councils Together on Trams/Trams Team meeting, 8 September 2022

Minutes of the Community Councils Together on Trams/Trams Team meeting on Thursday 8 September 2022 at 5:15pm, at Trams project compound (165 Leith Walk)

Actions and decisions are red italic. ‘TT’ means ‘Trams Team’. Names are mostly abbreviated to initials. Continue reading

Northbound road closure: impact on Leith Walk traffic from 2 October for 3 weeks CORRECT MAP

Following on from this post, we understand that we were supplied the wrong map. What we believe to be the right map is below, and has been put into the original post. LHNCC’s web-weaver apologises for any inconvenience this honest mistake causes.

map of affected area

Click the image to see the full-size PDF.

Northbound road closure: impact on Leith Walk traffic from 2 October for 3 weeks

Antigua Street – Annandale Street north-bound road closure

On the 2 October 2022 there will be changes to the traffic management arrangements on the north-bound section of Leith Walk between Antigua Street and Annandale Street to allow final surfacing works to be undertaken .

This will involve a full north-bound road closure for approximately three weeks from the Picardy Place turnback to Annandale Street. Please note the Picardy Place turnback will remain operational throughout the duration of these works.

Buses will be using the Picardy turn back. Bus stops on York Place will still be in use and they will be using East London Street and Annandale Street to get back onto Leith Walk.

There will be diversion signage installed in the local area to inform road users of the recommended route. The main diversion route for north-bound cyclists will be Dublin Street, Abercromby Place, Albany Street, Broughton Street and East London Street while traffic will be diverted via Dundas Street, Brandon Terrace, Canonmills, Broughton Road and Bonnington Road. Traffic will also be able to access Broughton Street via York Place and the Picardy Place turnback but this will only be signed in the local vicinity in order to encourage traffic to use the above diversion. Details of Lothian Buses diversions will be listed on their website.

Continue reading

Minutes of the Community Councils Together on Trams/Trams Team meeting on Wednesday 19 May 2022 at 5:30pm, at Trams project compound (165 Leith Walk)

Minutes of the Community Councils Together on Trams/Trams Team meeting on Wednesday 19 May 2022 at 5:30pm, at Trams project compound (165 Leith Walk)

Continue reading

Community Councils Together on Trams/Trams Team meeting, 25 November 2021

Community Councils Together on Trams/Trams Team meeting, 25 November 2021

Actions and decisions are red italic. ‘TT’ means ‘Trams Team’. Names are sometimes abbreviated to initials. Continue reading

Community Councils Together on Trams/Trams Team meeting, 26 November 2020

Minutes of the Community Councils Together on Trams/Trams Team meeting
(Construction Phase) via Google Meet on Thursday 26 November 2020 at 5:30pm Continue reading

Tram Diversion Route Resurfacing Work – Revised Programme

(from an email from Edinburgh Council, time-stamped Wed, 3 Jul 2019 at 15:51)

I write to provide an update to my ongoing carriageway resurfacing programme in and around Leith prior to the commencement of the work to extend the tram to Newhaven.

Works on site at Pilrig Street junction, Dalmeny Street and East London Street are due to complete at the end of next week (Friday 12 July) after which time the main contractor has a company recess for 2 weeks.

On returning to site on the 29 July, the work to redesign the junction at Duke Street and Easter Road will fully commence (some preparatory work will take place next week) while the majority of work ongoing elsewhere will be predominantly carriageway resurfacing work.

To this effect, please find below a basic table detailing the proposed locations, dates and traffic management for the resurfacing work and I have also attached the full programme in the form of a Gantt chart. I will caveat this and remind everyone that dates are approximate as any delays can have a knock on effect, however the order of work should remain the same and I will update EdinTravel as works progress.

I will also explain that the programme has extended due to additional work being requested and some issues on site with traffic signal installations however the main resurfacing work should throw up little in the way of unforeseen delays and there will be no further additional work included in the programme unless it is deemed important and we create space in the existing programme. We also remain in full contact with the team leading the Tram extension with regards their preparatory work and start date.

As before, residents and traders will receive notices prior to the start of work in their area with more specific details, and I will forward a copy of these notices on as appropriate. If you have any queries or concerns, please do not hesitate to contact me.

Month Date (Duration) Location Time Proposed Traffic Management
July 9 (2 days) East London Street Day Road Closure
29 (7 days) North Leith Sands Day Road Closure
29 (35 days) Duke Street R’about Redesign Day Retain roundabout as long as possible
August 7 (5 days) Great Junction Street Day Southbound loop using Henderson?
7 (9 days) Duncan Place Day Road Closure
8 (21 days) Links Place Traffic Islands Day Road Narrowing
15 (4 days) Gordon Street Day Road Closure
20 (3 days) Ocean Drive Day Road Closure.1 side at a time.
20 (12 days) Pilrig Street Day Road Closure in 2 phases
26 (6 days) Annandale Street Day Road Closure
September 2 (12 days) Bonnington Road Night Road Closure in 2 phases
9 (5 days) Broughton Street Night Road Closure
18 (12 days) Newhaven Road Night Road Closure in 2 phases
20 (21 days) Easter Road Night Phased road closures, road narrowing
October 10 (12 days) Broughton Road Night Road Closure in 2 phases
17 (2 days) East Hermitage Pl Junction Night 3 phase TTL’s – Close Links Gdns
28 (5 days) Portland Place Night Eastbound Closure using Ocean Drive
28 (10 days) Links Place Night Road Closure in 2 phases
November 4 (6 days) Academy Street Night Road closure, Duke St eastbound closure

Kind regards

Steven Blacklaw ¦ Engineer – Transport Design & Delivery
Place ¦ Planning & Transport ¦ The City of Edinburgh Council ¦ G4, Waverley Court, 4 East Market Street, Edinburgh EH8 8BG
Tel 0131 529 3252 steven.blacklaw@edinburgh.gov.uk

More detail on carriageway resurfacing works – Summer 2019/20

Following on from this post, Edinburgh Council has just sent the following detail about the road resurfacing planned for this summer.

Location Planned Start Date Estimated Duration Work Detail
Broughton Street 28-May + 22 Aug 4 weeks + 2 weeks Pedestrian crossing upgrade + carriageway resurfacing
Albany Street 03-Jun 1 week Carriageway resurfacing
Hopetoun Street 07-Jun 2 days Carriageway resurfacing
Academy Street 11-Jun 1 week Overlay setts
Dalmeny Street 17-Jun 10 days Carriageway resurfacing, overlay setts and minor footway works
East Hermitage Place 26-Jun 3 days Carriageway resurfacing
Portland Place 28-Jun 1 week Carriageway resurfacing
McDonald Road 01-Jul 10 days Footway widening and carriageway patching
Easter Road/Duke Street 01-Jul 8 weeks Junction redesign
East London Street 02-Jul 7 weeks Pedestrian crossing upgrade and carriageway resurfacing
Duncan Place 10-Jul 2 weeks Carriageway resurfacing and minor footway works
Great Junction Street 10-Jul 1 week Carriageway resurfacing
Gordon Street 02-Aug 1 week Carriageway resurfacing
Bonnington Road 08-Aug 3 weeks Carriageway resurfacing
Ocean Drive 08-Aug 3 days Carriageway resurfacing
North Leith Sands 13-Aug 1 week Carriageway resurfacing and minor footway works
Newhaven Road 26-Aug 2 weeks Carriageway resurfacing
Annandale Street 29-Aug 7 weeks New pedestrian crossings and carriageway resurfacing
Broughton Road 05-Sep 2 weeks Carriageway resurfacing
Easter Road 11-Sep 3 weeks Carriageway resurfacing and minor footway works
Links Place 23-Sep 4 weeks Carriageway resurfacing, new traffic island and footway works
Pilrig Street 29-Sep 4 weeks Carriageway resurfacing, new traffic island and footway works