(adapted from an email from Michael Morton, of Turner & Townsend Limited, sent on 17 January 2017 at 12:55)
The contractor commenced back on site on 5th January, carrying out site set-up on Iona Street as before and stakeholder communication, following which the works to the Pilrig Street junction commenced with a closure of Pilrig Street as of the 9th January for a period of around 8 weeks (early March completion). These works will also include works to the Iona Street junction and the surfacing of Leith Walk at these junctions. This will be the main focus of our Contractors’ work at this time as we seek to minimise disruption to pedestrians and traffic by opening a number of work sites concurrently. Work sites will then progress south on Leith Walk from Pilrig Street to McDonald Road as originally envisaged, with any additional work sites being opened only where…