Progress update
All work is currently running on schedule to the programme timescale
Section 6a West (Balfour Street southwards):
- All kerbs re-laid south of Balfour Street
- 75% of existing slabs removed
- 25% of new slabs re-laid
Section 6a East (Jameson Place southwards)
- 50% of existing slabs removed
- 15% new slabs re-laid
- Trial hole to relocate lighting column completed
Section 8a West (Jane Street southwards)
- 40% of existing slabs removed
- New gully connection complete
- Installation of kerbs 50% complete
- 20% of new slabs re-laid
Section 8a East (South of Manderston Street)
- 50% of existing slabs removed
- Installation of kerbs 75% complete
- 15% of new slabs re-laid
Other sections:
- Snagging works to sections 5 and 7 on-going
Looking ahead for next week:
- Continue with footpath works in all sections
- Relocate lighting columns in sections 6 and 8
- Gully installation at Stead’s Place