Location Planned Start Date Estimated Duration Work Detail
Broughton Street 28-May + 22 Aug 4 weeks + 2 weeks Pedestrian crossing upgrade + carriageway resurfacing
Albany Street 03-Jun 1 week Carriageway resurfacing
Hopetoun Street 07-Jun 2 days Carriageway resurfacing
Academy Street 11-Jun 1 week Overlay setts
Dalmeny Street 17-Jun 10 days Carriageway resurfacing, overlay setts and minor footway works
East Hermitage Place 26-Jun 3 days Carriageway resurfacing
Portland Place 28-Jun 1 week Carriageway resurfacing
McDonald Road 01-Jul 10 days Footway widening and carriageway patching
Easter Road/Duke Street 01-Jul 8 weeks Junction redesign
East London Street 02-Jul 7 weeks Pedestrian crossing upgrade and carriageway resurfacing
Duncan Place 10-Jul 2 weeks Carriageway resurfacing and minor footway works
Great Junction Street 10-Jul 1 week Carriageway resurfacing
Gordon Street 02-Aug 1 week Carriageway resurfacing
Bonnington Road 08-Aug 3 weeks Carriageway resurfacing
Ocean Drive 08-Aug 3 days Carriageway resurfacing
North Leith Sands 13-Aug 1 week Carriageway resurfacing and minor footway works
Newhaven Road 26-Aug 2 weeks Carriageway resurfacing
Annandale Street 29-Aug 7 weeks New pedestrian crossings and carriageway resurfacing
Broughton Road 05-Sep 2 weeks Carriageway resurfacing
Easter Road 11-Sep 3 weeks Carriageway resurfacing and minor footway works
Links Place 23-Sep 4 weeks Carriageway resurfacing, new traffic island and footway works
Pilrig Street 29-Sep 4 weeks Carriageway resurfacing, new traffic island and footway works